Sunday, April 5, 2009

Starting

We are so close! A lot has happened in a month. No, we have not poured the foundation yet, but almost. Not long after my last post, we had 24 eighteen wheeler loads of base delivered to our place- left over from a job. So we had a guy come out and use it to build a road (driveway) from the county road to the house. It only took half of the base, so we still have plenty for the foundation. He also dug out 6 inches of ground where the foundation is going to be laid. We also had the water company come in and install our water line and meter. AND the bank approved us for our loan. So we are making progress! A crew is going to come out tomorrow and start forming for the foundation. Then the plumber will need a few days to get things set up. And who knows what else, but we are almost there!